Select your location for location specific information:
If explosive substances are to be used for blasting, the local trade supervisory office or mining authority must be notified.
Morellstraße 30 d
86159 Augsburg
86136 Augsburg
Maximilianstraße 39
80538 München
Hinweis: Wir empfehlen eine vorherige Terminvereinbarung bei persönlichen Vorsprachen
80534 München
Explosive substances have a wide range of applications and are used, for example, in quarries or tunnel construction.
In the commercial sector, compliance with the requirements of the Explosives Act is generally monitored by the trade supervisory offices of the governments. The mining authorities are responsible for commercial blasting in underground cavities and in companies subject to mining supervision.
The notification of blasting with explosive substances must be made by the person holding the permit in accordance with the Explosives Act.
The notification must include
Changes that are associated with an increased risk must also be reported. Applications must be made to shorten the deadline.
The notification must be submitted with the required documents to the trade supervisory office or mining authority responsible for the location where the blasting is to be carried out.
The notification must be made using the form (see "Forms"). This can also be used to notify changes that are associated with an increased risk or to apply for a shortened deadline.
The notification is free of charge.
If the deadline is shortened: in the standard case EUR 75.00 plus expenses (deviations from this are possible in the case of increased expenditure)
The notification must be received at least 4 weeks before the start of the blasting if several similar blasts are to be carried out within a site or for the implementation of a project.
At least 1 week is required before any other blasting.
Exceptions to the notification period are possible under certain conditions. If the notification deadline is not met, an application must be made to shorten the deadline. This application must contain a comprehensible justification and be received by the office as early as possible so that the office has sufficient time to process the application. There is no legal entitlement to a shortened deadline.
The intended blasting only needs to be notified, a permit is not issued.
Blasting in facilities approved under immission control law does not have to be notified if the approval includes the blasting.
Blasting in companies subject to mining supervision does not have to be notified if a company plan permit has been issued for the blasting work.
When handling explosive substances, the requirements of the Explosives Act (SprengG) must be observed.